IRS Finally Releases Clarifications to PTC “Start of Construction” Guidance

Aug 8, 2014

Reading Time : 6 min

I. Clarification of Physical Work of a Significant Nature

The IRS in Notice 2013-29 provided two options for a project to be deemed to have met the statutory standard for tax credits of starting construction in 2013.  Five percent of the ultimate total cost of the project could be incurred in 2013 to meet a safe-harbor.  Alternatively, if a project did not meet the 5 percent safe-harbor in 2013, it could still be deemed to have started construction in 2013 if “physical work of a significant nature” was undertaken in 2013 (the “Physical Work Test”). 

Notice 2013-29 provided examples of such work that included excavating a foundation, pouring concrete for a foundation, installing anchor bolts, building integral roads and working on a custom-designed step-up transformer (the “Examples of Significant Work”).  However, Notice 2013-29 also included an example in which 20 percent of the turbine site’s excavation was completed, concrete was poured and anchor bolts installed.  This example created a concern that the Physical Work Test arguably required satisfaction of a 20 percent threshold.

Notice 2014-46 puts that concern to rest. It provides that the 20 percent example was “not intended to indicate that there is a 20 percent threshold or minimum amount of work required to satisfy the Physical Work Test. Assuming the work performed is of a significant nature, there is no fixed minimum amount of work or monetary or percentage threshold required to satisfy the Physical Work Test.” The foregoing statement could appear to raise the question: Although there is no fixed minimum, how does a project owner know that the work done was “of a significant nature”?

Notice 2014-46 provides clear comfort on that issue.  With respect to the Examples of Significant Work, it provides “Beginning work on any of the activities described above will constitute physical work of a significant nature.” The word “beginning” seems particularly helpful as it makes it clear that the Examples of Significant Work need not have been completed in 2013.

II. Transfers of Grandfathered Projects

The industry had requested that the IRS clarify that a developer could “start construction” in 2013 to qualify its project for tax credits and then sell or otherwise transfer the project to another party.2  The guidance in Notice 2014-46 is more restrictive than what the industry requested. 

The notice provides that a transfer is permissible, so long as either (a) the transferor or transferee is at least 20 percent related3 or (b) the property transferred does not consist “solely of tangible property (including contractual rights to such property under a binding written contract).”  Although not expressly referenced, the 20 percent option is similar to the principles of FAQ 23 of Treasury’s Begun Construction Cash Grant4 guidance, while the option to transfer more than merely tangible property is similar to the principles of FAQ 24 of that guidance.5  However, Notice 2014-46 is far more opaque in this respect than the Treasury FAQs.

For instance, FAQ 23 provides that the 20 percent related requirement applies “immediately before or immediately after,” while the notice is silent as to how long the parties must remain related.  Further, FAQ 24 has an example in which safe-harbor equipment is transferred along with “permits, a power purchase agreement and an interconnection agreement,” and the FAQ confirms that is sufficient, while no example is included in the notice.  Nonetheless, it would seem reasonable that transfer of the equipment for a project along with permits, a power purchase agreement and an interconnection should be sufficient for tax credit grandfathering purposes.  Further, if the project is intended to be merchant, the power purchase agreement should not be required.

In addition, as land rights are not “tangible personal property,” it should be permissible to transfer the grandfathered equipment along with only title to land for the project, a leasehold interest in land for the project or an option to acquire either of the foregoing.

What the government has communicated in its concern with respect to transfers of grandfathered equipment under the Cash Grant program was “trafficking” in grandfathered equipment, i.e., a financial investor purchasing equipment prior to the tax credit deadline, with little or no intent in actually developing a project, and then selling the equipment for a premium to a buyer seeking to qualify a project for tax credits. The trafficking concern should not be present so long as contracts that require time and expense to acquire, such as interconnection and power purchase agreements, are transferred with the tangible personal property.

III. Five Percent Safe-Harbor Clarification

Although not requested by the wind industry, the notice clarifies what happens if the amount incurred for a project in 2013 turns out to be less than 5 percent of the ultimate “total cost of the project.”  The notice provides that, if the project is composed “of multiple facilities” (e.g., multiple wind turbines), the tax credit eligible portion can just be reduced until “total cost” of the tax credit eligible portion is not in excess of 20 times the amount incurred in 2013.  The notice has an example in which only three of five turbines in a wind project are deemed to be tax credit eligible due to the total cost of all five turbines exceeding 20 times the amount incurred in 2013.6

What the notice does not clarify is how to handle the cost of improvements that are used by both the tax credit eligible and the tax credit ineligible portion, such as roads and transformers.  Must such common improvements be completely attributed to the tax credit eligible portion? Or can the cost of such common improvements be prorated between the tax credit eligible and the tax credit ineligible portions?  Prorating would appear to be the more equitable, but possibly not permissible, as transmission and most roads are “integral” to the tax credit eligible portion of the project.7

Although the notice is opaque in certain areas it should be welcomed by the wind industry.  The notice should result in many wind projects that were on hold moving forward at an expedited pace. 

Projects will need to be on an accelerated schedule in order to be “placed in service” by the end of 2015 as is necessary to avoid scrutiny from the IRS regarding whether they were “continuously constructed” from January 2014 forward.  As the notice was released almost three months after it was first previewed by a Treasury lawyer at a bar association meeting,8 it would have been equitable if notice had also shifted the deadline to avoid continuous construction scrutiny from December 31, 2015, to March 31, 2016.  As such a deadline is not statutorily mandated, it would have been in the IRS’s discretion to grant such leniency. 


1 A Treasury lawyer speaking at an American Bar Association conference on May 9 had summarized the industry’s requests.  A blog post discussing the Treasury lawyer’s statements is available here.

2 This issue arises whether “start of construction” was deemed to occur by satisfying the 5 percent safe-harbor or by meeting the Physical Work Test in 2013.

3 The notice refers to Internal Revenue Code Section 197(f)(9)(C), which provides a 20 percent standard.

4 The Cash Grant is provided for in Section 1603 of division B of the American Recovery and Reinvestment Act, as amended.  For wind and solar projects, the Cash Grant is 30 percent of “eligible basis.”  Solar projects have until the end of 2016 to be “placed in service”; however, a preliminary Cash Grant application must have been filed before the end of 2012.  Wind projects must have been placed in service before the end of 2012.

5 The guidance is available here.

6 The notice has a second example involving a biomass facility that cannot be divided into multiple facilities; thus, the biomass facility, if it missed the 5 percent safe-harbor, is only tax credit eligible if it met the Physical Work Test in 2013.

7 See Section 5.01(1) of Notice 2013-29 (defining “total cost” as “All costs properly included in the depreciable basis of the facility are taken into account to determine whether the Safe Harbor has been met. The total cost of the facility does not include the cost of land or any property not integral to the facility.”). 

8 See note 1, supra.

Share This Insight

Previous Entries

Speaking Energy

October 27, 2025

On October 23, 2025, the Secretary of the U.S. Department of Energy (DOE) directed the Federal Energy Regulatory Commission (FERC) to conduct a rulemaking to assert jurisdiction over load interconnections to the bulk electric transmission system and establish standardized procedures for the interconnection of large loads.1 The Directive included an advanced notice of proposed rulemaking (ANOPR) that sets forth the legal justification for asserting jurisdiction over transmission-level load interconnections and fourteen principles that should inform FERC’s rulemaking process. The Secretary has directed FERC to take “final action” on the Directive no later than April 30, 2026.

...

Read More

Speaking Energy

October 24, 2025

On October 21, 2025, the U.S. Department of Energy (DOE) issued a final order (DOE/FECM Order No. 5264-A1) granting Venture Global CP2 LNG, LLC long-term authorization to export up to 1,446 billion cubic feet per year of domestically produced liquefied natural gas (LNG) from its Louisiana facility to countries without a free trade agreement with the United States (Non-FTA Countries). The final order follows a March 2025 Conditional Order,2 which issued while DOE was still completing its review of the agency’s 2024 LNG Export Study.3 The final order confirms that the project’s export volume and term authorization (through December 31, 2050) are unchanged, but provides for a three-year “make-up period” to allow export of any approved volume not shipped during the original term.

...

Read More

Speaking Energy

October 9, 2025

On October 1, 2025, the Federal Energy Regulatory Commission (FERC or the Commission) issued Order No. 914 amending certain Commission regulations to incorporate a conditional sunset date in compliance with the Trump administration’s April 2025 Executive Order, “Zero-Based Regulatory Budgeting to Unleash American Energy” (the EO).

...

Read More

Speaking Energy

October 8, 2025

Akin is pleased to serve as a gold sponsor for Infocast’s Energy Independence Summit in Houston, October 21-23. Energy partner Charlie Ofner will moderate the Macroeconomics of Domestic Energy Independence panel, projects & energy transition partner Shariff Barakat will lead Opportunities in US Manufacturing: How Big, How Fast, How FEOC?, and counsel Taha Qureshi will guide the discussion on Cornerstones for Energy Independence: Investing in Grid Security & Cybersecurity.

...

Read More

Speaking Energy

October 6, 2025

As of October 6, 2025, the Federal Energy Regulatory Commission (FERC) continues to operate despite the lapse in appropriations that resulted in a government shutdown on October 1, 2025. While FERC receives appropriations from Congress, it primarily is self-funded through fees and charges obtained from the industries it regulates, offsetting its total costs. Hence, during prior government shutdowns in 2018 and 2013, the agency was able to continue operations. However, FERC published a plan for operating in the event of a lapse in appropriations on September 30, 2025, available here

...

Read More

Speaking Energy

September 8, 2025

On September 4, 2025, the Senate Energy and Natural Resources Committee convened a hearing to consider the nominations of Laura Swett and David LaCerte to serve as commissioners at the Federal Energy Regulatory Commission (FERC or Commission). Swett is a former FERC Staff that served as legal and policy advisor to former FERC Chairman Kevin McIntyre and Commission Bernard McNamee. LaCerte is an attorney in private practice that previously held positions at the Chemical Safety and Hazard Investigation Board and the Louisiana Department of Veterans Affairs.

...

Read More

Speaking Energy

September 9, 2025

On August 29, 2025, Christopher Wright, the Secretary of the U.S. Department of Energy (DOE) submitted a proposal to the Federal Energy Regulatory Commission (FERC) under section 403 of the Department of Energy Organization Act (DOE Organization Act), asking that FERC terminate its long-running proceeding in Docket No. PL18-1, which addresses proposed updates to its policy statement on the Certification of New Interstate Natural Gas Facilities. The docket resulted in a draft policy statement that has never been finalized, nor relied upon by FERC in a published order, but would require FERC to consider environmental impacts and potential mitigation prior to making a public interest determination under the Natural Gas Act (NGA). The Secretary asks FERC to rescind the draft policy statement in its entirety to remove any uncertainty in gas infrastructure development. Rescission would require FERC to initiate a new docket and develop a new record should it want to reinitiate similar policy changes in the future.

...

Read More

Speaking Energy

August 15, 2025

On August 8, 2025, the Federal Energy Regulatory Commission (FERC) issued an enforcement order in Skye MS, LLC (Skye) and levied a $45,000 civil penalty on an intrastate pipeline operator in Mississippi, resolving an investigation into the operator’s violations of section 311 (Section 311) of the Natural Gas Policy Act (NGPA). FERC faulted the operator for providing a Section 311 transportation service without timely filing a Statement of Operating Conditions (SOC) and obtaining FERC’s approval for the transportation rates. Section 311 permits intrastate pipelines to transport interstate gas “on behalf of” interstate pipelines without becoming subject to FERC’s more extensive Natural Gas Act (NGA) jurisdiction, but requires the intrastate pipeline to have an SOC stating the rates and terms and conditions of service on file with FERC within 30 days of providing the interstate service. Under the NGPA, Section 311 rates must be “fair and equitable” and approved by FERC. In Skye, FERC stated that the operator began providing Section 311 service on certain pipeline segments in Mississippi in May 2023, following their acquisition from another Section 311 operator, but did not file an SOC with FERC until April 2025. The order ties the penalty to the approximately two-year delay between commencement of the Section 311 service and the SOC filing date. The pipeline operator was also ordered to provide an annual compliance report and to abide by additional verification requirements related to the filing of its FERC Form No. 549D, the Quarterly Transportation & Storage Report for Intrastate Natural Gas and Hinshaw Pipelines.

...

Read More

© 2025 Akin Gump Strauss Hauer & Feld LLP. All rights reserved. Attorney advertising. This document is distributed for informational use only; it does not constitute legal advice and should not be used as such. Prior results do not guarantee a similar outcome. Akin is the practicing name of Akin Gump LLP, a New York limited liability partnership authorized and regulated by the Solicitors Regulation Authority under number 267321. A list of the partners is available for inspection at Eighth Floor, Ten Bishops Square, London E1 6EG. For more information about Akin Gump LLP, Akin Gump Strauss Hauer & Feld LLP and other associated entities under which the Akin Gump network operates worldwide, please see our Legal Notices page.